Feels like another busy week with lots of building and administrative activity.
Our actron aircon, shower screens, mirrors has been installed.
House has also been cleaned last Friday (28/10/16).
Final invoice has been released by MJH. For the last payment we will be doing that via bank cheque.
Massive congratulations to Stephen Kinnell and his wife as they just welcome a new baby into their lives last week. Steve will be off for 3 week. Our CLO advised that Shane De La Mare the area manager will be looking after our build. Will be giving Shane a call within the next few day to discuss progress and etc.
Main Image
Sunday, 30 October 2016
Friday, 21 October 2016
Painting Completed - Fitout Started
Been a very busy week for our build this week and felt like they did quite a bit.
Painting has officially been completed today (21/10/16). When we were out on site on Tuesday they have already completed some of the fitout i.e. toilets, butler pantry sink and etc.
Also very glad that we picked Apache Stone for our home theatre wall. Looks pretty schmick in my opinion.
Painting has officially been completed today (21/10/16). When we were out on site on Tuesday they have already completed some of the fitout i.e. toilets, butler pantry sink and etc.
Also very glad that we picked Apache Stone for our home theatre wall. Looks pretty schmick in my opinion.
Sunday, 16 October 2016
Electrical Fitout + Painting and Benchtops
Internal painting is still going and looks like it will be done once the electrical fit out has been completed. External painting of down pipes, eaves and etc has been completed though.
We were onsite on Saturday morning and to our surprise a team of 5-6 electricians was on site doing our electrical fitout. Looks like all of the downlights has been installed by 11am.
Walk in Robe, butler pantry and linen shelving has also been installed. Our bathroom and ensuite benchtop has been installed. Our kitchen benchtop has been partially installed.
We were onsite on Saturday morning and to our surprise a team of 5-6 electricians was on site doing our electrical fitout. Looks like all of the downlights has been installed by 11am.
Walk in Robe, butler pantry and linen shelving has also been installed. Our bathroom and ensuite benchtop has been installed. Our kitchen benchtop has been partially installed.
Sunday, 9 October 2016
Painting and Staining Started
Painting and staining started on Thursday (6/10/16). By Saturday when we were on site they have finished painting the ceiling and architraves in Illusive White.
The undercoat and staining of our entry and lin1 door has also been completed.
The undercoat and staining of our entry and lin1 door has also been completed.
Monday, 3 October 2016
Garage Door Installed.
Arrived on-site this morning to catch up with our SS. To my surprise the garage door has been installed over the long weekend.
Sunday, 2 October 2016
Tiling Done, Cabinets started.
To our pleasant surprise the tiling for our bathroom, ensuite and laundry has been completed over the weekend. The tiler was there finishing up our bathroom when we arrived on-site.
Laundry cabinets has been installed and completed. They have started the installation of kitchen and butler pantry cabinetry.
Study nook table has also been installed.
Subscribe to:
Posts (Atom)