Ryde Facade

Sunday, 26 June 2016

Frames and Windows delivered

Our frames and windows was delivered a few days ago. Spoke to our CLO and was informed we should get a call in the next few days with an update. Frame should start in the next few days as well.









Sunday, 12 June 2016

SLAB!

Our slab went down last Friday!!(10/6/16). Only had time to go check it out today.

It's great to finally see some progress and still mighty impress with the speed of MJH. Our Slab supervisor Ryan have been fantastic and is always and willing to help.

We were told frame should start in two weeks time.













Thursday, 2 June 2016

Form work and piering

Today we met our slab supervisor Ryan. Great guy, very friendly and knowledgable. Gave us the run down of next steps and timeline. If all things goes to plan than the slab will be done by next Wednesday.

We provisioned 50 lineal metre of piering in our contract, but only needed 39 lineal metre so we should get approximately $1000 credit back.





Friday, 20 May 2016

Officially on construction list

We were informed today that we are officially on the construction list! 

Work will begin within 20 working days

Monday, 16 May 2016

Commencement letter released to MJH!

Things are finally starting to move at an reasonable rate! Our lender have sent through the commencement letter to McDonald Jones Home today!

Hopefully MJH gets back to us with an official start date sometime this week. 

Wednesday, 4 May 2016

Plans approved by CDC!

Got our CDC approval earlier today!

If all things goes to plan we should be on the construction list by the end of next week.

Monday, 7 March 2016

Land is finally registered!!

After what feels like an eternity our little block of land is finally registered!

Settlement has been set for 22/03/16.