Arrived on-site this morning to catch up with our SS. To my surprise the garage door has been installed over the long weekend.
Main Image
Ryde Facade
Monday, 3 October 2016
Sunday, 2 October 2016
Tiling Done, Cabinets started.
To our pleasant surprise the tiling for our bathroom, ensuite and laundry has been completed over the weekend. The tiler was there finishing up our bathroom when we arrived on-site.
Laundry cabinets has been installed and completed. They have started the installation of kitchen and butler pantry cabinetry.
Study nook table has also been installed.
Sunday, 25 September 2016
Fixout Completed - Lock Up
We were informed on Friday that our fix out has been completed. Meaning all architraves and internal doors have been put in and the front door has been locked and we no longer have access unless the tradies forgets to lock up.
Kitchen, Bathroom and Laundry cabinet has also been delivered and wet area has been waterproofed.
Finally get to see our Lin 1 doors in person and so glad we went with them as a feature item in our house. These doors still needs to be stained in Caoba.
Kitchen, Bathroom and Laundry cabinet has also been delivered and wet area has been waterproofed.
Finally get to see our Lin 1 doors in person and so glad we went with them as a feature item in our house. These doors still needs to be stained in Caoba.
![]() |
| Double Sliding Lin 1 Home Theatre Doors |
![]() |
| Butler Pantry Door (Left) Laundry Door (Right) |
![]() |
| Front door |
![]() |
| Bathroom Cabinets |
![]() |
| Entry Hall Way + Amazing Wife |
![]() |
| Kitchen, Laundry and ensuite cabinets |
Friday, 16 September 2016
Gyprock & Architraves Completed - Rendering started
Been about two week since we have been on-site. The build is still progressing rather well with gyprock and architraves being completed earlier in the week.
They have also started rendering our facade, seems like the second coat have just been applied. Just waiting on the final top coat.
The house definitely feels a lot bigger after the architraves are installed.
They have also started rendering our facade, seems like the second coat have just been applied. Just waiting on the final top coat.
The house definitely feels a lot bigger after the architraves are installed.
Friday, 2 September 2016
Rough-In Appointment
Had our rough-in appointment today which went for almost an hour. Everything was where it was meant to be so no issue whatsoever.
Also had a good chat with our SS and he thoroughly walked us through what they will be doing for the next couple of weeks. Looks like we will hit lock up by end of September or there about.
Very impressed with our SS, he has great attention to detail and very open and honest with everything. He was happy for us to bring our independent inspector and told us to send him the report so he can go through it to make sure he hasn't missed anything.
Our independent inspector was very impressed with the quality of work on our build. There was one or two very minor issue that needs to be address but besides that it was pretty much spot on.
Insulation and Gyprock will start next week, should be done by next Friday.
We are still targeting to get keys before christmas.
Also had a good chat with our SS and he thoroughly walked us through what they will be doing for the next couple of weeks. Looks like we will hit lock up by end of September or there about.
Very impressed with our SS, he has great attention to detail and very open and honest with everything. He was happy for us to bring our independent inspector and told us to send him the report so he can go through it to make sure he hasn't missed anything.
Our independent inspector was very impressed with the quality of work on our build. There was one or two very minor issue that needs to be address but besides that it was pretty much spot on.
Insulation and Gyprock will start next week, should be done by next Friday.
We are still targeting to get keys before christmas.
Friday, 19 August 2016
Roof tiles on! - Gutter and Fascia completed!
Gutter and fascia was completed earlier in the week.
To our surprise the roof tiles is about 95% done and they only started the roof tiles this morning. I assume they had a massive team onsite today. The roof tiles will be completed by Monday.
To our surprise the roof tiles is about 95% done and they only started the roof tiles this morning. I assume they had a massive team onsite today. The roof tiles will be completed by Monday.
Friday, 12 August 2016
Bricking almost done!
Been a little while since we have been on site due to work commitment and the rain delaying the build.
Bricking is almost done, should be completed first thing monday morning. Fascia and gutter is due to start on Monday and roof tiling on Wednesday (17/8/16)
Bricking is almost done, should be completed first thing monday morning. Fascia and gutter is due to start on Monday and roof tiling on Wednesday (17/8/16)