Ryde Facade

Sunday 17 July 2016

Bricks are delivered

Bricks are delivered last Friday (15/7/16). Been advised by our SS that bricklayers are onsite "loading up the job" ready to start bricking on Wednesday.






Tuesday 5 July 2016

Frames completed!

Was informed our frames have been completed yesterday.

Perfect timing as it's about to rain in Sydney for the next few days.












Saturday 2 July 2016

Frames!


Frames started three days ago on the 30th of June. They completed 90% of the frames on the first day! Very impressed with the speed of our build. Frames should be completed early next week. 

Met our SS Anthony yesterday and couldn't have asked for a better SS to look after our build.